July 2022
Work on the Leeward Bikeway continues. Estimated completion date summer of 2023
Contractor completed paving work for the bike path between Kapolei Parkway and Philippine Sea Road. Contractor working on installing paving blocks by Philippine Sea Road. Asphalt paving has been complete from Philippine Sea Road to Kapolei Parkway, between Kapolei Parkway and Fort Weaver, and between Fort Weaver Road and West Loch. Shoulder dressing work remains.
Contractor working on grading work between West Loch towards Waipahu.
Kapakahi Stream Pedestrian Bridge – Contractor is working on the installation of the temporary beam support for the utility relocation work. Once the utilities are relocated, the existing bridge can be demolished.
Waikele Stream Pedestrian Bridge : Contractor is working on the installation of the temporary beam support for the utility relocation work. Once the utilities are relocated, the existing bridge can be demolished.